Contractor liability and compensation
Questioner
In a cooperation agreement, the contractor has committed to executing the issued environmental permit. The contractor did not continue construction for 26 weeks, which is why the municipality withdrew the environmental permit. Can I hold the contractor liable on the basis of Article &:854 of the Dutch Civil Code and claim compensation for damages?Lawyer
Do you mean article 7:854 BW? That article concerns suretyship and therefore does not apply if there is no suretyship agreement. If a contractor has contractually committed to carrying out an environmental permit and fails to do so, damages may be claimed by the party affected by the failure to build.Take the next step
Don't keep questions about your situation to yourself. Ask your question and get a personal answer from an experienced lawyer.